We do full installation and ESD certification. We can install your Forbo ESD tile and make sure its ESD certified. We are among the few companies that do this. With over 2 million square feet of ESD flooring installed, we are the one-stop choice for your ESD needs.
ColoRex® must be installed on a flat.
smooth, rigid, clean and permanently dry subfloor. The moisture
content of concrete
subfloors should not exceed 2.5% when measured according to the
CM method or 5 Ibs./1000 sq.ft. in 24 hours when tested according
to ASTM F 18069. Prior to installation, the ColoRex® tiles must
be acclimatized for at least 24 hours at a minimum temperature
of 18°C. Temperature should remain constant before, during
and 48 hours after installation. Use a copper strip for earth connection.
The use of a conductive acrylic dispersion Forbo adhesive is recommended.
Apply the adhesive following the manufacturer's instructions.
Roll floor with a 50 kg roller. Seam welding and flash cove skirting
are optional. Homogeneous welding is possible for the finishing
of inner and outer corners.
For ESD protective installations
do not apply any wax or floor finish as they might reduce the
conductive properties of the floor.

ESD Flooring Maintenance
Routine maintenance of ColoRex® should consist of sweeping
the floor with impregnated one-way tissues or spray buffing with
a red pad at low speed, using a specific, neutral and wax-free
cleaning solution. Spray buffing is also the ideal solution for
raised access floors.
If the wet method is preferred for routine maintenance, damp
mop the floor with a neutral detergent only and rinse well.
For large areas with heavy traffic, the use
of a scrubber drier machine with a specific detergent is indicated.
For extraordinary maintenance procedures such as construction
end cleaning or restorative maintenance, please ask for our detailed
manuals.
|